IEC/R Two Year Planning Timeline
⬇ Download The IEC/R two-year Planning Timeline
-
24 Months Before IEC/R
- IEC/R Mentor should be confirmed 24 months ahead of IEC/R.
- USAR team submits IEC/R Application to INSARAG Secretariat (minimum of two years ahead of intended date).
-
23–1 Months Before IEC/R
- Ongoing updates of INSARAG Secretariat by IEC/R Mentor.
-
22 Months Before IEC/R
- INSARAG Secretariat Completes Review of A-PoE.
- Based on A-PoE, INSARAG Secretariat/Mentor recommends "Go/No Go". If "Go" INSARAG Secretariat allocates Provisional Date.
- If "No Go" INSARAG Secretariat confirms such with USAR team and discusses alternative plan.
-
13 Months Before IEC/R
- IEC/R Classifier Team Leader and INSARAG Secretariat Representative selected and assigned.
-
10 Months Before IEC/R
- IEC/R Classifiers selected.
-
12 Months Before IEC/R
- USAR team submits C-PoE to INSARAG Secretariat.
- INSARAG Secretariat forwards C-PoE to IEC/R Team Leader.
-
6 Months Before IEC/R
- IEC/R Team Leader/Mentor recommends "Go / No Go" to INSARAG Secretariat.
-
4 Months Before IEC/R
- If "Go" INSARAG Secretariat confirms date with USAR team.
- INSARAG Secretariat opens the event on the VO.
- If "No Go" INSARAG Secretariat confirms such with USAR team and mentor to discuss an alternative plan.
- IEC/R team reviews exercise plan and time line and receives update on exercise site.
-
24–1 Months Before IEC/R
- Ongoing final planning and preparation with IEC/R Mentor.
-
Within 14 Days After IEC/R
- IEC/R team completes report within 14 days and submits to INSARAG Secretariat.
-
Within 30 Days After IEC/R
- INSARAG Secretariat IEC/R Report Delivery to the USAR team within 30 Days.
-
After Report Delivery (TBD)
- Follow up Activities with IEC/R Team Leader/Mentor – TBD.